Flushing Away Liability: What the Aqua Engineering Case Means for Contractors and Subcontractors

The recent Town of Mancos v. Aqua Engineering case is an insightful example of how well written contracts and timely legal action can make all the difference in resolving disputes between municipalities, general contractors, and subcontractors.  The ruling favored Aqua Engineering; a subcontractor that played a role in a wastewater treatment facility project gone wrong.  The court’s decision highlighted key legal principles, including the economic loss rule and the importance of well-structured contracts in construction disputes.  Whether you are a subcontractor looking to avoid undue liability or a general contractor seeking to ensure subcontractors shoulder their fair portion of responsibility, this case offers valuable lessons for all parties involved in construction projects.

The Background: A Wastewater Project with Issues

In 2008, the Town of Mancos, Colorado, hired Souder, Miller & Associates (“SMA”) to design a new wastewater treatment facility.  SMA subcontracted Aqua Engineering to help implement a specific wastewater treatment system known as the Multi-Stage Activated Biological Process (“MSABP”).  However, after construction, the facility never worked as expected.  For years, the Town faced ongoing issues, and despite Aqua’s involvement in attempts to fix the problems, the facility remained dysfunctional.

By 2018, the Town filed a lawsuit against Aqua, SMA, and others, alleging negligence, breach of contract, misrepresentation, and violations of the Colorado Consumer Protection Act (“CCPA”).  The lawsuit sought to hold Aqua liable for its role in the design and implementation of the project.

The Economic Loss Rule: A Key Factor

Aqua’s defense relied heavily on the economic loss rule, which played a pivotal role in the court’s ruling.  This legal doctrine bars tort claims, like negligence, when the loss is purely financial and stems from a breach of contractual duties.  In Aqua’s case, its duties were outlined in a Subconsultant Agreement with SMA, not the Town of Mancos.  Therefore, the court found that the Town could not sue Aqua for negligence, since Aqua’s obligations were defined by its contract with SMA, not the Town, and the losses were purely financial.

This ruling emphasized a key point for both general contractors and subcontractors: when the responsibilities are clearly defined in contracts, liability is largely limited to contractual obligations absent an independent duty of care.  Since this was not a residential project, the court found that Aqua owed the Town no independent duty of care.  Appropriately analyzing the duty of care helps keep disputes within the bounds of the contract rather than expanding into tort claims, like negligence, which carry broader implications.

No Contract, No Liability

The court also dismissed the Town’s breach of contract claim against Aqua for a simple reason: there was no contract between the Town and Aqua.  The Subconsultant Agreement between SMA and Aqua explicitly stated that the contract did not create third-party beneficiary rights for the Town.  Without such a provision, the Town could not claim Aqua had breached any contractual obligation toward it.

For general contractors and subcontractors, this is an important lesson in ensuring that contracts clearly specify which party holds the liability and to which party.  If a subcontractor’s duties are only to the general contractor, the subcontractor can avoid direct legal exposure to the client (such as a municipality or property owner) unless there is a specific third-party beneficiary clause in place, or a finding that the third-party is an implied third-party beneficiary of the contract.

Statute of Limitations: Why Timing Matters

Another important aspect of this case was the court’s ruling on the statute of limitations.  The Town’s misrepresentation and CCPA claims were dismissed because they were filed too late.  The court found that the Town knew about the facility’s defects as early as 2012, but it did not file its lawsuit until 2018, well beyond the applicable three-year statute of limitations found in C.R.S. §  6-1-115.

This part of the ruling is a reminder for both contractors and subcontractors that timing is critical in legal disputes.  If there are issues with a project, it is important to act within the timeframe allowed by law to avoid missing the window to bring a claim.

Key Takeaways for Subcontractors and Contractors

The Town of Mancos v. Aqua Engineering case offers valuable lessons for both subcontractors and general contractors.  Here is what each party can learn:

For Subcontractors:

Strong Contracts are Your Best Defense: Aqua’s success in this case rested on its well-defined Subconsultant Agreement with SMA.  The contract clearly outlined Aqua’s duties and ensured that Aqua’s obligations were only to SMA, not the Town.  Subcontractors should ensure their contracts precisely define their responsibilities and limit third-party claims where possible. Note that this only applies where there is no independent duty of care, such as in residential construction.  See AC Excavating v. Yacht Club II Ass’n.

The Economic Loss Rule is a Powerful Shield: The court’s reliance on the economic loss rule demonstrates how subcontractors can limit liability to contractual obligations.  If your duties are outlined in a contract, you may be able to avoid tort claims like negligence, which can be more difficult to defend.

Be Mindful of Timelines: The statute of limitations saved Aqua from potential misrepresentation and CCPA claims.  Subcontractors should track project timelines and be aware of when a statute of limitations may protect them from delayed legal action.

For General Contractors:

Clear Contracts Ensure Accountability: To avoid shouldering all the liability for a claim, general contractors should structure contracts that clearly outline subcontractor duties and liabilities.  Ensure that each party’s role is well-defined and include provisions that allocate responsibility where it belongs.

Consider Third-Party Beneficiary Clauses: If you want to ensure your client (such as a municipality or property owner) has direct recourse against a subcontractor, consider including a third-party beneficiary clause in your contracts.  This allows the client to hold subcontractors accountable without going through the general contractor.

Indemnification Clauses are Key: Clearly drafted indemnity clauses can help general contractors ensure that subcontractors take on their fair share of the risk and potential legal costs in the event of a dispute.

A Balanced Approach to Risk

For both subcontractors and general contractors, the Town of Mancos case highlights the importance of well-drafted contracts and clear lines of responsibility.  Subcontractors benefit from limiting liability to the scope of their contractual duties, while general contractors must ensure they have adequate risk-sharing provisions to avoid bearing the brunt of legal disputes.

Ultimately, the case serves as a reminder that when things go wrong on a project, having a solid contractual foundation can make all the difference in how liability is assigned and how disputes are resolved.

Archives

To learn more about our firm, call or e-mail us today to schedule a meeting with a member of our team